Seawolf (SSN-21) Commissioned

1997

7

0

Seawolf Program Terminated

1992

2

0

Seawolf Construction Starts

1989

10

0

Seawolf Construction Contract awarded to EB

1989

1

0

Detailed Design Contract for Seawolf signed with Newport News

1987

4

0

Complete Prelimnary Design of Seawolf

1985

5

0

Start Preliminary Design of Seawolf

1983

12

0

Start Formal Feasibility Studies of Seawolf

1982

12

0

Design /Construction Contract for Trident Signed with EB

1974

7

0

Triton (SSN 586) Completes Circumnavigation of the World

1960

4

25

After being commissioned on 11/10/1959, Triton set out to circumnavigate the world following Magellan;'s route.


The actual submerged circumnavigation occurred between 24 February and 25 April 1960, covering 26,723 nautical miles (49,491 km; 30,752 mi) in 60 days and 21 hours at the average speed of 18 knots (33 km/h; 21 mph) while crossing…

Start of Triton (SSN 586) Circumnavigation of Wolrd

1960

2

24

After being commissioned on 11/10/1959, Triton set out to circumnavigate the world following Magellan;'s route.


The actual submerged circumnavigation occurred between 24 February and 25 April 1960, covering 26,723 nautical miles (49,491 km; 30,752 mi) in 60 days and 21 hours at the average speed of 18 knots (33 km/h; 21 mph) while crossing…

Triton (SSN 586) Commissioned

1959

11

10